Construction Underway

As of Q2 2025 construction of the Cowboy Aggregates limestone quarry has begun. Since construction we have extracted 130K tons of aggregate and established 15+ miles of road.

In June of 2025 we began advancing civil, road, and rail works. All materials sourced on-site, reducing transport costs, increasing efficiency, and ensuring quality control. We anticipate switchgear installation for the UP rail network connection in early 2026.